July 15, 2023 - Council District 5
- EPS Variances
- Planning Board Meetings
- Sewer Project Perry Hall Manor
- Sewer Relining Project Bowley’s Quarters, Carroll Island and White Marsh (Bengies/Bird River)
- Red House Run Structural Sewer Rehabilitation
- Herring Run Basin 17 and 33 Relief Sewer
- East Branch Herring Run Relief Sewer
- Development Meetings and Zoning Hearings
EPS VARIANCES
The Department of Environmental Protection and Sustainability (EPS) publishes a list of the environmental administrative variance requests along with their status. The requests are listed by County Council District.
Information: EPS Variances for District 5
PLANNING BOARD MEETINGS
The board will meet as follows:
- Thursday, July 20, at 4:30 p.m.
- In-person in the Jefferson Building Hearing Room, 105 West Chesapeake Avenue, Room 104, Towson, Maryland 21204
Please check the Planning Board page for the meeting agenda, meeting procedures and any last-minute schedule changes.
Information: Contact Taylor Bensley by phone at 410-887-3482 or by email at tbensley@baltimorecountymd.gov.
SEWER PROJECT PERRY HALL MANOR
The Department of Public Works and Transportation is connecting 104 homes in the Perry Hall Manor area in a long-term project to provide sewer service. In September, residents saw topographical and environmental surveyors gathering information for the design phase. The surveyor work has been completed for the moment, though more field work is anticipated. Construction is expected to begin next year and will take from one to one-and-a-half years to complete.
Information: Email engineering@baltimorecountymd.gov.
SEWER RELINING PROJECT BOWLEY’S QUARTERS, CARROLL ISLAND AND WHITE MARSH (BENGIES/BIRD RIVER)
There is more than five miles of small- and large-diameter sewer relining in this project costing $3.6 million. The work is scheduled to be completed in the fall.
Information: Email engineering@baltimorecountymd.gov.
RED HOUSE RUN STRUCTURAL SEWER REHABILITATION
Baltimore County has started a major sewer rehabilitation project consisting of almost 15 miles of sewer line in the Overlea and Rosedale areas. Work on the $4.7 million project began in June 2022 and is expected to take about a year and a half to complete. It's approximately 35 percent toward completion and should be finished by the end of this year. The Red House Run Structural Sewer Rehabilitation project is part of the County's Consent Decree—the County’s agreement with the U.S. Environmental Protection Agency to improve the entire sanitary system and eliminate sanitary sewer overflows.
Information: Email engineering@baltimorecountymd.gov.
HERRING RUN BASIN 17 AND 33 RELIEF SEWER
Baltimore County has started a major relief sewer project consisting of installing 5,400 linear feet of 15-to-18-inch sanitary sewer main at a cost of $6.5 million dollars. The project is scheduled to be completed in October.
The work to be performed in Basin 17 North is located east of Collinsdale Road between Asgard Court and Deanwood Road, generally following parallel to an existing sewer line within both County drainage, a utility easement and private property. The work to be performed in Basin 17 South is located east of the terminus of English Oak Road, generally following parallel to an existing sewer line within both County drainage, a utility easement and private property. The work to be performed in Basin 33 is between Redwood Avenue and Beverly Avenue, generally following parallel to an existing sewer line within both County drainage, a utility easement and private property.
Information: Email engineering@baltimorecountymd.gov.
EAST BRANCH HERRING RUN RELIEF SEWER
Baltimore County has started a major relief sewer project consisting of installing 11,232 linear feet of eight-to-36-inch sanitary sewer main at a cost of $16.1 million dollars. The project limits start at the Baltimore City line at Perring Parkway to Taylor Avenue and east beyond the Harford Park community. The project is scheduled for completion in December.
Information: Email engineering@baltimorecountymd.gov.
DEVELOPMENT MEETINGS AND ZONING HEARINGS
Development Meetings include Community Input, Concept Plan, County Review, Development Review Committee and Hearing Officers Hearings.
Zoning Hearings include Special Exceptions, Variances and other issues before the Office of Administrative Hearings of Baltimore County.
These meetings are virtual through Webex.
Please check the Development, Zoning Hearings and Meetings Calendar for links to the meetings, information on participating in the virtual meeting, the meeting agendas and any last-minute schedule changes.
For further information, please call the Department of Permits, Approvals and Inspections at 410-887-3391 or email paizoning@baltimorecountymd.gov. You may also contact the Office of Administrative Hearings at 410-887-3868.