June 15, 2024 – Council District 5
- EPS Variances
- Planning Board Meetings
- Juneteenth Celebration
- Sewer Project Perry Hall Manor
- Bird River and Bengies Sewershed Repair, Replacement and Rehabilitation
- Red House Run Structural Sewer Rehabilitation
- East Branch Herring Run Relief Sewer
- Development Meetings and Zoning Hearings
EPS Variances
The Department of Environmental Protection and Sustainability (EPS) publishes a list of the environmental administrative variance requests along with their status. The requests are listed by County Council District.
Information: EPS Variances for District 5
Planning Board Meetings
The board will meet virtually through Webex as follows:
- Thursday, June 20, at 4 p.m.
Please check the Planning Board page for the meeting agenda, meeting procedures and any last-minute schedule changes.
Information: Contact Taylor Bensley by phone at 410-887-3482 or by email at tbensley@baltimorecountymd.gov.
Juneteenth Celebration
Join the Department of Recreation and Parks for this year’s Juneteenth Celebration on Saturday, June 15, at 10 a.m. at Benjamin Banneker Historical Park and Museum, 300 Oella Avenue, Catonsville, Maryland 21228. Visit the past through living history presentations, enjoy live music from local bands, explore and shop vendor and exhibitor booths, and sample a variety of cuisines from our food vendors. Register on the CivicRec online platform. Admission and parking is free.
Sewer Project Perry Hall Manor
The Department of Public Works and Transportation is connecting 104 homes in the Perry Hall Manor area in a long-term project to provide sewer service. In September 2022, residents saw topographical and environmental surveyors gathering information for the design phase. The surveyor work has been completed for the moment, though more field work is anticipated. Construction is expected to begin this year and will take from one to one and a half years to complete.
Information: Email engineering@baltimorecountymd.gov.
Bird River and Bengies Sewershed Repair, Replacement and Rehabilitation
There are more than five miles of small- and large-diameter sewer relining in this project costing $3.6 million. The work is 99 percent complete.
Information: Email engineering@baltimorecountymd.gov.
Red House Run Structural Sewer Rehabilitation
Baltimore County has started a major sewer rehabilitation project consisting of almost 15 miles of sewer line in the Overlea and Rosedale areas. Work on the $4.7 million project began in June 2022. It's approximately 85 percent toward completion. The Red House Run Structural Sewer Rehabilitation project is part of the County's Consent Decree—the County’s agreement with the U.S. Environmental Protection Agency to improve the entire sanitary system and eliminate sanitary sewer overflows.
Information: Email engineering@baltimorecountymd.gov.
East Branch Herring Run Relief Sewer
Baltimore County has started a major relief sewer project consisting of installing 11,232 linear feet of eight-to-36-inch sanitary sewer main at a cost of $16.1 million dollars. The project limits start at the Baltimore City line at Perring Parkway to Taylor Avenue and east beyond the Harford Park community. The project is 95 percent complete.
Information: Email engineering@baltimorecountymd.gov.
Development Meetings and Zoning Hearings
Development Meetings include Community Input, Concept Plan, County Review, Development Review Committee and Hearing Officers Hearings.
Zoning Hearings include Special Exceptions, Variances and other issues before the Office of Administrative Hearings of Baltimore County.
These meetings are virtual through Webex.
Please check the Development, Zoning Hearings and Meetings Calendar for links to the meetings, information on participating in the virtual meeting, the meeting agendas and any last-minute schedule changes.
For further information, please call the Department of Permits, Approvals and Inspections at 410-887-3391 or email paizoning@baltimorecountymd.gov. You may also contact the Office of Administrative Hearings at 410-887-3868.